AWPR = Mortgaging Your Future
When the former Transport Minister Tavish Scott announced his preference for a significantly longer route choice, 46km compared with 30 km for the previous preferred option, for the AWPR in December 2005, he also announced his intention to fund the AWPR through a Public Private Partnership, or PPP.
The concept of a PPP or Private Finance Initiative (PFI) is fairly straightforward. Instead of buying a road and then operating it itself, the Scottish Executive, and Aberdeen City and Shire, enter into a long-term contract with the private sector to do so. Regular payments are then made for the services and assets over the life of the contract; in the case of the AWPR 30 years.
A 30 year PPP repayment schedule more than doubles the cost, compared to just paying the out right cost of the project.
Specific examples of costs and repayments are provided below.
|
Mid Case Transport Scotland
|
Mid Case Transport Scotland |
UK 2005 Average Cost at £15.3 million per mile |
Cost at £20 million per mile
|
Total AWPR Cost Estimate
[Pre VAT] |
£345,000,000
|
£345,000,000
|
£437,000,000
|
£572,000,000
|
Fastlink Cost Estimate [Pre VAT]
|
£82,500,000
|
£82,500,000
|
£105,000,000
|
£137,000,000 |
| Loan Number of Years |
30
|
30
|
30
|
30 |
| Loan Interest Rate [%] |
7%
|
7%
|
7%
|
7% |
| Include VAT ? |
No
|
Yes |
Yes |
Yes |
| Summary Loan Amounts |
£345,000,000
|
£405,375,000
|
£513,475,000
|
£672,100,000
|
| Scottish Executive Contribution |
£295,125,000
|
£346,771,875
|
£439,356,000
|
£574,986,250
|
| Aberdeen City Contribution |
£24,937,500 |
£29,301,563 |
£37,059,500 |
£48,556,875 |
| Aberdeenshire Contribution |
£24,937,500 |
£29,301,563 |
£37,059,500 |
£48,556,875 |
Scottish Executive Repayment Details
|
Scheduled Annual Payment
|
£23,783,062
|
£27,945,098
|
£35,406,120 |
£46,336,074
|
Total Interest Payments
|
£418,366,870 |
£491,581,072
|
£622,827,597 |
£815,095,969 |
Total Principal Payments
|
£295,125,000 |
£346,771,875 |
£439,356,000 |
£574,986,250 |
Total Payments
|
£713,491,870 |
£838,352,947 |
£1,062,183,597
|
£1,390,082,219 |
Individual Councils Repayment Details
|
Scheduled Annual Payment
|
£2,009,623
|
£2,361,308
|
£2,986,492
|
£3,913,024
|
Total Interest Payments
|
£35,351,203
|
£41,537,664 |
£52,535,255 |
£68,833,843
|
Total Principal Payments
|
£24,937,500 |
£29,301,563 |
£37,059,500 |
£48,556,875 |
Total Payments
|
£60,288,703 |
£70,839,226 |
£89,594,755 |
£117,390,718 |
|
|
|
|
|
| Download Payment Schedules |
|
|
|
|
From the above, even the very optimistic cost estimates and VAT assumptions of the Scottish Executive result in Aberdeen City and Shire Council tax increases of £ 2 million per year for 30 years, and easily have the potential to rise to £ 4 million per year for 30 years assuming more realistic cost and VAT estimates.
This is effectively Mortgaging Your Future on a road development scheme that is unlikely to deliver any of the long term traffic benefits that the AWPR project team promise.
Should you be a concerned Transport Minister, MSP, MP, local Councillor or member of the Public you can download our free and easy to use AWPR Loan Calculator, using the link below.